Developer Report Card: RNA Address, 2 Years Behind Schedule And Languishing


RNA Address
RNA Address

Buyers and investors of Mumbai-based RNA Corp’s ‘RNA Address’ project are an angry lot. They claim that the developer has not completed construction on the project, in spite of having promised to deliver it 2 years ago.

Buyers Allege Project Delays, Unpaid Rent

RNA Address was launched in 2010 and delivery was promised in 2014. However, buyers claim that construction on the project has stopped and that there is no clear timeline on when they will get delivery of their dream homes.

“In 2013, construction on the project stopped and by then most of us had made 60% of the total payment. Since then we have been following up with the builder but there is very little communication about what is happening,” claims Srinivas Sadaipali, a buyer in the project.

The project also includes a redevelopment component, where the company has promised to take care of the rentals of the original home owners of the plot, while their new homes are being constructed. But here too, there are allegations that the company has broken its word.

“There is no work going on and we are like refugees on our own land. We can do nothing about it,” says a bitter Robert D’Souza, whose building was demolished for redevelopment by the developer.

“We were told that the project will be completed in 3-4 years but now it’s been 8 years, and there is no sign of completion. Earlier we used to get rent on time, but now there is a problem in that also,” claims another homeowner who did not want to be named.

NDTV sent a detailed questionnaire to the company on these issues, but we have not received any response from the company so far. Frustrated by the experience, some home buyers have filed cases in the consumer courts and other are exploring legal options.

Edited by Nikhil Narayan Sivadas, NDTV

3,477 thoughts on “Developer Report Card: RNA Address, 2 Years Behind Schedule And Languishing

  1. Admiring the time and effort you put into your website and in depth information you offer. It’s awesome to come across a blog every once in a while that isn’t the same out of date rehashed material. Fantastic read! I’ve saved your site and I’m adding your RSS feeds to my Google account. generic viagra

  2. you’re really a good webmaster. The web site loading speed is incredible. It seems that you’re doing any unique trick. Moreover, The contents are masterpiece. you have done a wonderful job on this topic! metronidazole.

  3. Hey there would you mind sharing which blog platform
    you’re using? I’m looking to start my own blog in the near future but I’m having a difficult time selecting between BlogEngine/Wordpress/B2evolution and
    Drupal. The reason I ask is because your design and style
    seems different then most blogs and I’m looking for something completely
    unique. P.S Apologies for being off-topic but I had to ask!

  4. I believe what you published made a lot of sense. But,
    what about this? what if you typed a catchier title? I mean,
    I don’t wish to tell you how to run your blog, but what if you added a post title to possibly
    grab a person’s attention? I mean Is Allegra D 12 Hour Non Drowsy – Rx Meds Blog is kinda boring.
    You should glance at Yahoo’s home page and note how they
    create news titles to get viewers interested.
    You might try adding a video or a picture or two to grab readers interested about what you’ve got to say.
    Just my opinion, it could bring your blog a little livelier.

  5. I have been surfing on-line more than three hours these days,
    yet I never found any attention-grabbing article like yours.
    It is lovely price sufficient for me. In my opinion, if all website owners and bloggers made excellent content material as you did, the internet shall be a lot more
    useful than ever before.

  6. It is the best time to make some plans for
    the future and it’s time to be happy. I have learn this submit and if
    I could I desire to recommend you few fascinating issues or suggestions.
    Perhaps you can write next articles referring to this article.

    I want to read more things approximately it!

  7. I think that is among the such a lot significant information for me.
    And i am glad studying your article. However wanna observation on few common things, The site style is wonderful, the articles is really excellent : D.
    Good job, cheers

  8. After looking at a few of the blog posts on your web site, I honestly appreciate your technique of writing a blog. I saved as a favorite it to my bookmark webpage list and will be checking back soon. Please visit my web site as well and tell me your opinion.Thank you for the sensible critique. Me and my neighbor were just preparing to do some research on this. We got a grab a book from our local library but I think I learned more clear from this post. I am very glad to see such wonderful info being shared freely out there. cbd kratom

  9. I truly love your website.. Excellent colors & theme. Did you make this website yourself?
    Please reply back as I’m attempting to create my very own website and want to
    know where you got this from or just what the theme is named.
    Thank you!

  10. I’ve been browsing online more than three hours lately, but I by no means found any
    interesting article like yours. It is pretty price sufficient for me.

    In my view, if all site owners and bloggers made just right content
    as you did, the internet will likely be much more helpful than ever before.

  11. One thing is that when you are searching for a student loan you may find that you will need a cosigner. There are many scenarios where this is true because you should find that you do not have a past credit ranking so the lender will require that you’ve got someone cosign the loan for you. Great post.

  12. Hi, I do think this is a great web site. I stumbledupon it 😉 I may return yet again since I bookmarked it.
    Money and freedom is the greatest way to change, may you be rich and continue to guide others.

  13. Hola! I’ve been following your web site for a long
    time now and finally got the courage to go ahead and give you a shout out from
    Houston Tx! Just wanted to tell you keep up the excellent work!

  14. I absolutely love your blog.. Great colors & theme. Did you make this site yourself?
    Please reply back as I’m looking to create my very own website and would like to
    find out where you got this from or exactly what the theme is called.
    Many thanks!

  15. I have been browsing on-line greater than 3 hours as of
    late, but I never found any fascinating article like yours.
    It’s lovely price sufficient for me. In my view, if
    all site owners and bloggers made just right content material
    as you did, the internet shall be much more useful than ever before.

  16. It’s the best time to make some plans for the future and it is time to
    be happy. I have read this post and if I could I want to suggest you
    some interesting things or tips. Perhaps you could write next
    articles referring to this article. I wish to read more things about it!

  17. It is perfect time to make some plans for the future and it’s time to be happy.
    I have learn this publish and if I may I desire to
    counsel you some fascinating things or tips. Perhaps you could write next articles
    referring to this article. I wish to read even more issues approximately it!

  18. I am not sure where you’re getting your information, but good topic.
    I needs to spend some time learning more or understanding more.
    Thanks for magnificent info I was looking for this information for my mission.

  19. Hey there! I’ve been following your site for a while now and finally got the bravery to go ahead and
    give you a shout out from Houston Texas! Just wanted to mention keep up the excellent work!

  20. Hello would you mind stating which blog platform you’re
    working with? I’m planning to start my own blog soon but
    I’m having a tough time making a decision between BlogEngine/Wordpress/B2evolution and Drupal.
    The reason I ask is because your layout seems different then most blogs
    and I’m looking for something completely unique.
    P.S My apologies for being off-topic but I had to ask!

  21. Hello, i read your blog occasionally and i own a similar one and i was just wondering if
    you get a lot of spam feedback? If so how do you prevent it, any plugin or anything you
    can suggest? I get so much lately it’s driving me insane so any help is very
    much appreciated.

  22. Hola! I’ve been following your blog for some time now and finally got the courage to go ahead
    and give you a shout out from Austin Texas! Just wanted to tell you
    keep up the good work!

  23. I’ll right away snatch your rss feed as I can’t in finding your email
    subscription link or newsletter service. Do you have any? Kindly let me recognize so
    that I may subscribe. Thanks.

  24. Hello, i think that i saw you visited my website so
    i came to “return the favor”.I am attempting to find things to enhance
    my web site!I suppose its ok to use some of your
    ideas!

  25. Hi, I do think your blog could possibly be having web browser compatibility problems. When I take a look at your web site in Safari, it looks fine however, when opening in IE, it has some overlapping issues. I merely wanted to give you a quick heads up! Other than that, great blog!

  26. I am really loving the theme/design of your web site. Do you ever run into any web browser compatibility problems? A handful of my blog audience have complained about my blog not operating correctly in Explorer but looks great in Opera. Do you have any solutions to help fix this issue?

  27. Знаете ли вы?
    Кустурица пропустил получение «Золотой ветви» в Каннах, так как любит друзей больше, чем церемонии награждения.
    Планета — глазное яблоко может быть пригодна для жизни в одних районах и непригодна в других.
    Роден назвал свои «Врата ада» напрямую, а его соотечественник только намекнул.
    Мама и четверо детей снимают фильмы о своей жизни во время войны.
    Зелёный чай может быть розовым.

    http://0pb8hx.com

  28. After study a handful of the content in your website now, and i also really like your technique for blogging. I bookmarked it to my bookmark site list and will be checking back soon. Pls look at my web site as well and inform me how you feel.

  29. Знаете ли вы?
    Будущего чемпиона Европы по боксу в детстве одновременно дразнили «хохлом» и «москалём».
    Клирик-саксонец стать папой римским не захотел, а патриархом Севера не смог.
    Сооснователь и глава Социал-демократической партии Великобритании стал бароном.
    Искусствоведы спорили, смирилась ли со скорой смертью неизлечимо больная женщина на картине русского художника, а она прожила ещё 37 лет.
    Китай реализует в Пакистане собственный План Маршалла.

    0PB8hX

  30. Знаете ли вы?
    Зелёный чай может быть розовым.
    Старейшую в России организацию реставраторов велено было выселить и уплотнить.
    «Голова крестьянина» хранилась в доме у немецкой актрисы.
    Иногда для поддержки экономики деньги «разбрасывают с вертолёта».
    Старейший депутат Палаты представителей проработал в Конгрессе США почти до 92 лет.

    http://www.0pb8hx.com/

  31. Знаете ли вы?
    Среди клиентов древнеримского афериста был император Марк Аврелий.
    Консервативные художественные критики обрушились на портрет девушки, называя её гермафродитом, дочерью Каина и проституткой.
    Битву русских дружин и монголо-татар возле леса отмечают сразу в трёх селениях.
    Видеоигру с простейшей графикой называли и шедевром, и троллингом.
    Фиктивно отменить рабство в Камбодже её короля заставили французские колонизаторы.

    http://www.arbeca.net/

  32. Знаете ли вы?
    Видеоигру с простейшей графикой называли и шедевром, и троллингом.
    Копенгагенский собор пришлось выстроить заново после визита англичан в 1807 году.
    Член Зала хоккейной славы готов был играть где угодно, лишь бы не переходить в тренеры.
    Клирик-саксонец стать папой римским не захотел, а патриархом Севера не смог.
    Старейший депутат Палаты представителей проработал в Конгрессе США почти до 92 лет.

    arbeca

  33. Thanks for the suggestions you write about through this blog. In addition, quite a few young women that become pregnant usually do not even try and get health insurance coverage because they dread they wouldn’t qualify. Although a lot of states currently require that insurers present coverage despite the pre-existing conditions. Costs on these kinds of guaranteed options are usually bigger, but when thinking about the high cost of health care bills it may be the safer route to take to protect your current financial future.

  34. In January last year, wee vpgj72 flatten ill. It’s okay, just a temperate real viagra without a doctor prescription, which passed in five days. But the temperature without warning returned away the end of the month: the thermometer showed 40. The servant was urgently hospitalized with fever and convulsions. A few hours later, three-year-old Yegor stopped breathing – he prostrate into a coma. With the commandeer of a ventilator and a tracheostomy, the doctors resumed the trade of the lungs, but oxygen starvation struck the brain. The kid has lost everything that he managed to learn in three years. The diagnosis is posthypoxic encyphalopathy.

  35. Our doctor cerebration that Dad was conceivably uniform control superiors than Mom in this situation. Stricter, more persistent, when one pleases not mournfulness once again when you have need of to perform bad viagra online. Well, I wanted to hand out my missus a break.
    I used up a inconsequential exceeding a month in the intensive care unit and two and a half months in the bone marrow uproot unit. There I became a donor after my son. I’m ready I was able to cure him. I was the single man in both departments, but my parents were already there. That is, a man in the avert with a lady is no longer a rarity.

  36. We are currently on maintenance chemotherapy at emphasize, but every Thursday we go to the bureau in requital for tests and testing. A team a few of days ago they took a sternal puncture. We were in the quarter on some someday, as we were diagnosed with Lyme disease – we were delightful intravenous viagra generic and we are even now winning them.

  37. Anyone who has even seen a hasty laddie desire not be skilled to disregard it. Elfin fingers, husk thinner than series paper: further living is enclosed in an infinitely flimsy shell. All the hope of loved ones is on the skill of doctors who choice advise the mollycoddle outlast and develop. You can conceptualize how exacting it is as a replacement for both the child’s relatives and the doctors http://ed4rx.com cialis when there are methods of treating a infant in the mankind, but in this fatherland and in this burg they are not available. Let’s help the smallest ones pocket top-class medical care!

  38. Thanks for one’s marvelous posting! I truly enjoyed reading it, you might be a great author.I will make sure to bookmark your blog and may come back later in life. I want to encourage you to continue your great work, have a nice weekend!

  39. Howdy, i read your blog from time to time and i own a similar one and i was just curious if you get a lot of spam feedback? If so how do you prevent it, any plugin or anything you can advise? I get so much lately it’s driving me crazy so any assistance is very much appreciated.

  40. I am often to blogging and i actually admire your content. The article has actually peaks my interest. I am going to bookmark your site and preserve checking for brand spanking new information.

  41. I used to be more than happy to seek out this web-site.I wished to thanks for your time for this glorious learn!! I definitely enjoying every little little bit of it and I have you bookmarked to check out new stuff you weblog post.